St Georges Church of England School
A new three Storey teaching block at St Georges CoE School in Gravesend
Portfolio
Learn more about the broad variety of projects that we have completed in recent years.
View Project
A new three Storey teaching block at St Georges CoE School in Gravesend
Case study
Project value
6,000,000
Project type
New Build
Project length
64 weeks
A new three Storey teaching block at St Georges CoE School in Gravesend
What Did The Job Involve?
This project involved two phases of work. The new 3-storey teaching block, which was a steel frame construction on concrete piled foundations with ground beams, a precast concrete ground floor and upper floors. A mixture of brickwork and trespa cladding formed the envelope on SFS framing. Internally the building provided classrooms, dance studio, 6th form study area, meeting rooms, a large and associated stores and wc’s on each floor. Within the existing school general teaching spaces were turned into science rooms. This was completed over a summer holiday. The second phase involved the demolition of tow large concrete framed blocks and the remodelling of external areas with a mixture of hard and soft landscaping. The school was in occupation throughout except where the pandemic disrupted both school and construction.
What Were The Challenges?
One of the main challenges was the shared access. This had to be managed with the school by clear communication. The school is located within a residential area and the road leading to the school gates was particular tight. Manoeuvring piling rigs and large machinery proved a challenge but passed without incident. Also a Southern Water main sewer passed beneath the footprint of the building. At the time of commencement the formal agreement had not been concluded by the client and so this had to be maintained during the construction work and later diverted.
Beardwell’s Added Value
Ground breaking and topping out ceremonies were held on site involving the school. We also engineered and led a project to paint a school building using a select group of students. The project involved planning, procurement and production and served as an introduction to workflow planning. Regular liaison meetings were held with local residents. Ecology measures were introduced and donations of materials made within the school. Community wood recycling was also used where surplus timber was recycled within the community. We also assisted with the formation of a sanctuary garden comprising a small garden area.
View Project
Highworth Grammar School is an Ofsted Outstanding rated selective girls school catering for…
Case study
Highworth Grammar School
Project value
£2.5m
Project type
New build
Project length
36 weeks
Highworth Grammar School is an Ofsted Outstanding rated selective girls school catering for 1,500 pupils and located in Ashford, Kent. Boys are admitted within the 6th Form. Founded in 1904 the school moved to the present site in 1928 when many of the school buildings were constructed.
What Did The Job Involve?
For many years the School had an ambition to construct much needed indoor sports facilities and this was finally realised when funding was obtained. Designed by Ingleton Wood, we were awarded the project following a traditional tender route and collaborative VE exercise.
Known as the Vink Centre, after a former long-standing Governor of the school, the new building comprises a sports hall and associated stores and changing facilities, PE office and dance studio/multipurpose area situated on the first floor. The project also included the construction of a small MUGA to compensate for external hard play being lost. New service upgrades were provided to the site.
The building was a steel frame with brick, render and thermawood cladding. An excellent relationship with the school was enjoyed throughout.
What Were The Challenges?
Located to the rear of the school, the school’s main entrance had to be maintained throughout the day. Deliveries were scheduled to avoid busy times, and sensitive works such as service connections were completed out of hours. Access to the school playing fields and car park had to be maintained throughout the project and this included drop and collection at each end of the school day.
The Sports Hall roof required the erection of curved steel beams which were spliced on site due to their length. Curved steel roof panels were formed on site. This required additional space being created within the compound for the rolling machinery.
Beardwell’s Added Value
In association with teaching staff, we completed a number of curriculum-related exercises looking at design and construction technologies.
We hosted a sixth-form student for a period of work experience and were so impressed with Phoebe, that we invited her to complete a paid project for us on another contract during her summer holiday.
Site visits by pupils were entertained throughout the project.
View Project
Procured through our framework contract with Essex County Council we were appointed following…
Case study
Essex County Council
Project value
£1.6m
Project type
Mixed
Project length
36 weeks
Procured through our framework contract with Essex County Council we were appointed following a mini-competition to design and build a new two-storey building providing 5nr new classrooms, storage, WC’s and associated external works. The project included the removal of 3nr old RL units and the refurbishment of a classroom and toilet area in the old school building.
What Did The Job Involve?
This was a design and build secured on the Essex Construction Framework. Kingswode Hoe is a special school in Colchester. The brief was for the provision of a new teaching block incorporating new FT, Music and DT rooms and 2 no. general classrooms and the refurbishment of classrooms and a WC within the school. Design was managed by Beardwell and commenced at Stage 1. This included the completion of all surveys, building control approval, achievement of planning permission and scheduled monument consent.
The constraints of the site included avoiding undue disturbance to the ground, ensuring that external treatment was sympathetic to the existing buildings and avoiding encroachment onto the existing playing fields.
The 600 m2 building comprises a 40 T steel frame supported on traditional deep strip footings, with concrete ground and upper floor supported on a steel deck. The external walls are predominantly brick/block cavity walls. A platform lift provides disabled access to the first floor.
The project was delivered on time and budget.
What Were The Challenges?
Construction required working alongside archaeologists from CAT. This was managed smoothly with the ‘finds’ including roman coins being shown to the pupils.
The project was located on a tight occupied school in a residential area. Access to the site was only possible through the existing school carpark and so to avoid significant disruption we provided a temporary car parking area to the rear of site which was used by the School. The shared access had to be managed throughout the school day.
Being a live special school at both primary and secondary level there were a lot of inquisitive pupils. A secure boundary was formed and strict access arrangements applied.
The electrical power to site had to be upgraded without disrupting ongoing operations.
Beardwell’s Added Value
A temporary car park was provided to limit disruption. We also refurbished the Forest School shed without charge and organised site visits for pupils at various stages. This allowed the school to incorporate aspects of the project into the curriculum, including history and design technology.
The school had never had a ‘prom’ and following discussion, we raised in excess of £2,000 to help fund this event.
In addition, we volunteered staff to help at the summer fete where we facilitated various events including being soaked in the ‘stocks’.
View Project
The project for Stanway School involved two phases of work. The first comprised a new 710m2, 2-storey science and…
Case study
New Science, Art and Music Blocks
Project value
£5.6m
Project type
New build
Project length
52 weeks
The project for Stanway School involved two phases of work. The first comprised a new 710m2, 2-storey science and art block with multi purpose hall. The second a new 1650m2, 2-storey art, music and sports block. Both projects were located to the rear of the school. In addtion several areas of remodelling and refurbishment were completed within the school.
What Did The Job Involve?
Both buildings were constructed using a steel frame on pad and strip foundations, cast in-situ concrete slabs, Kingspan roof cladding and a combination of brick, render and curtain walling envelope.
Internally, all areas were completely fitted out including the provision of light weight internal partitions, floor and wall finishes, suspended ceilings, decorations and furniture. Overall the projects delivered 9 classrooms, 3 science labs, music practice rooms, new changing rooms and the associated w/c and corridors. Alongside the new build aspect, we also carried out internal refurbishments in multiple areas of the school including the gymnasium.
What Were The Challenges?
The main challenges with the project were working within a live school site, and the fact that the site was landlocked. In order to overcome this our Project Manager carried out meticulous logistical planning in coordination with the school to ensure that access routes for staff, pupils and deliveries always remained accessible to them. Deliveries to site were carefully timed to avoid peak times during the school day. Our site compound remained in place throughout the works but during the second phase we opted to erect a temporary bridge to access the site area. This provided a benefit to the school because the were able to maintain uniterupted key routes to the sports fields for the duration of the project.
Beardwell’s Added Value
Beardwell proactively seek opportunities to add value to their projects. In the case of Stanway we worked with the school to deliver social value throughout the project. This included conducting site tours for the governors, staff and pupils, organising charity football matches on the all weather sports pitch, staffing the school library at lunch time to allow pupil access, participating in the careers days including holding mock interviews with pupils and assisting the School’s Site Manager with minor works around the site.
View Project
Beardwell Construction were delighted to be chosen by The Royal Hospital School to undertake the refurbishment of the library….
Case study
Library Refurbishment
Project value
£310k
Project type
Refurb
Project length
8 weeks
Beardwell Construction were delighted to be chosen by The Royal Hospital School to undertake the refurbishment of the library. This continued an association with the School for whom we have now completed several projects.
What Did The Job Involve?
The work involved the complete strip out of the existing library area, some structural alterations, repairs to the structure including plastering of existing walls and soffits, the creation of new walls and glazed partitions, formation of bulkheads and extensive acoustic treatment throughout.
New electrical services and air treatment and ventilation were installed to create a modern comfortable space.
The mezzanine floor received new glazed balustrading and handrails. New Amtico ‘parquet’ flooring was installed to the whole area. The library was decorated and furniture installed including a new reception desk and small coffee point.
What Were The Challenges?
The project had to be completed within a very short timescale over the summer vacation.
Challenges included an ever-changing design which required a flexible approach to construction. The extent of plastering required to be undertaken meant that drying time had to be factored within a fast track programme. Also, the existing services and fabric brought up numerous challenges during the work, all of which had to be oversome without delay.
High level works necessitated the use of scaffolding and towers which created severe restrictions to the working areas below.
Funded by private donations the budget was fixed and required strict control. Our QS worked closely with the Client team to ensure that this was not compromised.
Beardwell’s Added Value
The project was delivered on time and to budget. This would not have been possible without an excellent working relationship with the School and their maintenance team who assisted with final connections and thereby ensured a smooth handover.